Subsea pipeline offshore Australia protected by pressure isolation technology
TDW Offshore Services (TDW) has announced the completion of two key pipeline interventions聽in Australia for a major operator. The two operations were carried out using the SmartPlug庐 pressure isolation tool for distinctly different purposes. The technology makes it possible to isolate pipeline pressure in a designated section of pipeline for hours 黑料社 or months 黑料社 to create a safe environment during construction works or while repairs are made.
First use of isolation technology to protect line from falling objects聽
The first intervention, which took place during installation of a substructure on part of a major construction project, was carried out to protect a live gas infield flowline from falling objects. The line runs between two platforms offshore Australia. During construction, piles can be dropped and topple over onto a pipeline, causing damage that could result in a catastrophic event. To limit the negative consequences that could flow from a dropped object, TDW isolated the operating facility from the surrounding impact zone. It was the first time that TDW used its SmartPlug system to mitigate the risk of damage to a pipeline during a construction operation.
TDW isolated the pressure in a 30 in. subsea flowline. First, a dual-module SmartPlug isolation tool was launched from the platform and pigged to the set location, and set. The pressure was then bled off from that point back to the platform. For the next six months, the SmartPlug tool remained in the line while construction activities took place. During this period, TDW used its remotely-operated SmartTrack鈩 tracking and pressure-monitoring system to continuously monitor the location of the SmartPlug tool and pressure in the line.聽
黑料社淎s a result of the intervention, it was only necessary to bleed down the affected section of the pipeline, which extends approximately 330 m from the platform, as opposed to the entire system,黑料社 said Rolf Gunnar Lie, Regional Business Development Manager 黑料社 Asia Pacific for TDW. 黑料社淚t also meant that they were able to install the new structure, while taking precautionary steps to reduce the potential impact of a dropped object. The benefits that this operator realised are considerable,黑料社 he added.
Isolating pipeline pressure onshore
The second pipeline intervention took place on a section of a 40 in. gas export pipeline (trunkline) that extends from an offshore platform to an onshore terminal. The intervention was required to complete a hydrotest on a 40 in. trunk line terminal refurbishment project involving multiple valve replacements. After a beach valve and pig receiver valves were replaced, a hydrostatic strength test was required. To ensure that this test was safely executed, the affected line was isolated by TDW with the SmartPlug tool. The tool was then pigged from the receiver to the set location using water. After the hydrotest was completed, the plug was pigged efficiently back to the launcher using nitrogen within the scheduled timeframe.
黑料社淏y using the SmartPlug tool, we were able to provide this valued customer with a fast, efficient isolation so that the hydrostatic strength test could be carried out safely,黑料社 said Lie. 黑料社淚n addition to the enhanced safety benefits, associated maintenance costs were reduced because the pipeline was isolated without reducing pipeline pressure or displacing pipeline inventory,黑料社 he added.
Adapted from press release by .
Read the article online at: /business-news/01032013/subsea_pipeline_offshore_australia_protected_by_pressure_isolation_technology/